Q:

Which of the following is determined as a direct result of computing the earliest starting and finishing times for the activities of a project network? maximum project duration which activities are on the critical path activity slack time variance in project duration expected project duration

Accepted Solution

A:
Answer:Expected project duration  is determined as a direct result of computing the earliest starting and finishing times for the activities of a project network.Step-by-step explanation:In project management, early start is the earliest moment at which a specific activity may start and early finish the earliest moment at which it can end. Early finish (es)  is computed as: EF = ES + d where d is the activity duration and ES early startEarly start is computed as ES: Max (EF-1) or the maximum early start of predecessory activities. Once we have calculated these values in the network for each activity , the early finish of last activity corresponds to the expected project duration, the earliest time in which we may finish the project if there are no issues. Max project duration is open question as we could have infinite delays or never finish the project. Time variance in project duration may only be estimated once we have actual execution times of our project. Slack time and critical path are obtained after obtaining the ES and EF but this info alone is not sufficient. We require either the late start or the late finish of the activities to calculate slack, Zaero slack activities, those that cannot be delayed form critical path and can only be obtained after having ES. EF. LS and LF